Export PDF Export Schedule

Application Details

Valuation Period

Statutory notice dates auto-calculate from this date on save.

Amounts

£
£
Update once the Payment Certificate is received.

Payer Response — Payment & Pay-less Notices

Record the notices received from the payer. A notice served after its deadline is ineffective under the Construction Act, so the full applied sum remains due.

Date the payer served their payment notice.
£
The sum the payer says is due.
Only if the payer intends to pay less than the notified sum.
£
The reduced amount the payer intends to pay.
The basis on which the sum is calculated (required for a valid notice).

Construction Act Statutory Dates

Auto-calculated from the application date and job contract type. Override manually if needed.

Last date the payer can issue a payment notice.
Last date the payer can issue a pay-less notice.
The date payment must legally be made.

Notes

Set via "Mark as Paid" action, or enter manually.
£
The sum actually received (may differ from the certified amount).