Final Account — Wishaw Sports Hall

Export PDF CVR
Final account
Draft
£103,078
Not yet agreed
Received to date
£0
Paid £0 + retention released £0
Outstanding
£103,078
Final payment £103,078 + retention £0
Final margin
£28,054 · 27.2%
Tender baseline 26.3%

Final account build-up

The agreed contract value: original sum, agreed variations and the final close-out adjustments.

Original contract sum £101,755
Agreed variations +£0
Remeasurement adjustment +£712
Loss & expense / claims +£611
Contra-charges / deductions +£0
Agreed final account £103,078

Settlement position

What's been certified, paid and retained against the final account.

Applied to date £0
Certified to date £0
Paid to date (net) £0
Retention held £0
— released £0
— outstanding £0
Final payment due now £103,078

Reconciliation vs CVR forecast

The agreed final account against the forecast out-turn from Cost Value Reconciliation.

CVR forecast value £101,755
Agreed final account £103,078
Variance vs forecast +£1,323
Forecast out-turn cost £75,024
Final margin £28,054 · 27.2%