Pricing & Margin: Eastwood Industrial Unit

Adjudication Factors

Cost Breakdown by Type

Labour £47,886.57 (44%)
Material £55,016.53 (51%)
Plant £3,183.77 (3%)
Subcontract £1,895.98 (2%)
Unclassified £0.00 (0%)

From line build-ups. "Unclassified" = direct-rate lines with no build-up.

Cost → Submission Price

Net measured cost £141,138.68
Prelims £0.00
Contingency / risk £0.00
Base cost £141,138.68
Overheads £0.00
Profit £0.00
Net sell price £141,138.68
Main contractor's discount £0.00
Submission Price £141,138.68
Margin on sell: 0% Mark-up on cost: 0%