Cost Value Reconciliation — Job #8

Export PDF Cost Ledger
Final Account
£90,021
Contract £90,021 + variations £0
Value Earned (99.2%)
£89,346
Applied £90,021
Cost to Date
£62,662
Accrual £0 · Committed £0
Margin to Date
£26,684 · 29.9%
Budget 30% · Forecast out-turn 29.9%

Cost analysis — budget vs actual, by resource

Tender cost budget (from BoQ build-ups) against actual cost incurred to date, broken down to individual resources so each can be attributed and tuned.

Resource type / item Budget cost Cost to date Committed Variance
Labour £27,873 £27,698 £176
Site supervision £14,153 £14,187 -£34
Installation labour £13,720 £13,511 £209
Material £30,748 £30,555 £194
Flashings & trims £12,046 £5,939 £6,106
Adhesives & primers £8,925 £4,437 £4,488
Single ply membrane £4,736 £6,941 -£2,205
Fixings & fasteners £2,902 £7,084 -£4,182
Insulation £2,140 £6,154 -£4,014
Plant £2,765 £2,747 £17
Scaffold hire £1,238 £1,619 -£381
Access platform (MEWP) £949 £0 £949
Scaffold inspection £578 £1,128 -£551
Subcontract £1,673 £1,662 £11
Scaffolding subcontract £795 £788 £7
Asbestos removal £705 £874 -£169
Specialist access £173 £0 £173
Total cost £63,059 £62,662 £397

Margin trend

Margin % across frozen CVR snapshots.

CVR history

Frozen reconciliation snapshots, one per valuation period.

Period end Value Cost Margin Margin %
28/06/2026 £44,335 £0 £44,335 100.0%
28/07/2026 £89,346 £394 £88,952 99.6%