Cost Value Reconciliation — Job #7

Export PDF Cost Ledger
Final Account
£488,059
Contract £488,059 + variations £0
Value Earned (74.3%)
£362,623
Applied £366,044
Cost to Date
£311,288
Accrual £0 · Committed £1,022
Margin to Date
£51,334 · 14.2%
Budget 21.6% · Forecast out-turn 14.2%

Cost analysis — budget vs actual, by resource

Tender cost budget (from BoQ build-ups) against actual cost incurred to date, broken down to individual resources so each can be attributed and tuned.

Resource type / item Budget cost Cost to date Committed Variance
Labour £170,762 £138,955 £31,807
Installation labour £90,955 £88,070 £2,885
Site supervision £79,807 £50,885 £28,922
Material £198,059 £161,168 £36,891
Fixings & fasteners £77,713 £43,289 £34,424
Insulation £51,923 £35,963 £15,960
Flashings & trims £51,362 £55,276 -£3,915
Adhesives & primers £11,272 £26,639 -£15,367
Single ply membrane £5,789 £0 £5,789
Plant £8,618 £7,013 £1,605
Scaffold hire £4,681 £0 £4,681
Scaffold inspection £2,127 £3,350 -£1,224
Access platform (MEWP) £1,810 £3,662 -£1,852
Subcontract £5,104 £4,153 £1,022 £951
Asbestos removal £2,489 £2,503 -£14
Scaffolding subcontract £1,713 £1,650 £62
Specialist access £903 £0 £903
Total cost £382,543 £311,288 £1,022 £71,254

Margin trend

Margin % across frozen CVR snapshots.

CVR history

Frozen reconciliation snapshots, one per valuation period.

Period end Value Cost Margin Margin %
02/03/2026 £78,666 £0 £78,666 100.0%
02/04/2026 £153,332 £50,360 £102,972 67.2%
02/05/2026 £228,093 £200,556 £27,537 12.1%
02/06/2026 £296,788 £246,345 £50,443 17.0%
02/07/2026 £362,623 £267,253 £95,369 26.3%