Cost Value Reconciliation — Job #5

Export PDF Cost Ledger
Final Account
£65,735
Contract £51,281 + variations £14,454
Value Earned (76.6%)
£50,344
Applied £50,835
Cost to Date
£35,382
Accrual £3,042 · Committed £382
Margin to Date
£14,962 · 29.7%
Budget 41.4% · Forecast out-turn 29.7%

Cost analysis — budget vs actual, by resource

Tender cost budget (from BoQ build-ups) against actual cost incurred to date, broken down to individual resources so each can be attributed and tuned.

Resource type / item Budget cost Cost to date Committed Variance
Labour £16,960 £15,576 £1,384
Site supervision £9,344 £9,157 £188
Installation labour £7,616 £6,419 £1,197
Material £17,158 £15,757 £1,401
Fixings & fasteners £7,691 £4,194 £3,497
Single ply membrane £3,616 £2,721 £895
Insulation £2,786 £2,324 £462
Flashings & trims £1,621 £2,834 -£1,213
Adhesives & primers £1,445 £3,684 -£2,240
Plant £2,613 £2,399 £213
Scaffold hire £1,050 £0 £1,050
Scaffold inspection £999 £1,206 -£207
Access platform (MEWP) £564 £1,193 -£629
Subcontract £1,796 £1,650 £382 £147
Scaffolding subcontract £1,118 £770 £348
Specialist access £678 £880 -£202
Total cost £38,527 £35,382 £382 £3,145

Margin trend

Margin % across frozen CVR snapshots.

CVR history

Frozen reconciliation snapshots, one per valuation period.

Period end Value Cost Margin Margin %
27/12/2025 £6,639 £0 £6,639 100.0%
27/01/2026 £13,977 £9,149 £4,828 34.5%
27/02/2026 £21,005 £10,991 £10,014 47.7%
27/03/2026 £26,821 £10,991 £15,829 59.0%
27/04/2026 £36,067 £17,894 £18,173 50.4%
27/05/2026 £38,533 £26,278 £12,255 31.8%
27/06/2026 £49,102 £31,955 £17,147 34.9%
27/07/2026 £50,344 £34,786 £15,558 30.9%